Forum Title: Top Flange TJI Hanger/Floor Level
Hello, I'm going to be GC for my home which is outside of my typical electrical work. There is a particular carpentry/foundation detail I am unsure of. The home will be have a walkout basement foundation likely with poured walls. I want to keep the rise from my poured front porch and garage as small as possible. I would like the porch to be within an inch or 2 and the garge within 1 step of interior floor level. The floor system will be 14 TJIs. I thought I could accomplish this with top flange hangers however the garage is at 30 degree. Here I believe there are many options possibly including an appropriately attached ledger. Any thoughts on the best way to do this or perhaps a link to a detail Thanks
Category: General Contractor Post By: NORA CUMMINGS (Goodyear, AZ), 02/15/2018