Seeking input on how much production is effected when working on projects with limited access that require all work be preformed from a two man boom lift. I am expecting about a 50% decrease in production from my crew on a upcoming job which will require the use of 80 ft lifts. We are replacing approximately 1000 lf of fascia on a historic building at the local college. In the past we have worked from 40ft lifts on other jobs and I noticed about a 20% decrease in my crews output. Anyone with much experience in working from a 80 ft lift have a comparison, 50% seems like a lot to me? Sent from my iPad using Tapatalk